Zix Datacenter UPS Maintenance

THIS IS A SCHEDULED EVENT Sep 24, 07:00 – 20:00 CDT

Sep 20, 09:54 CDT
Scheduled – The engineering team will be working with our UPS vendor and electricians to conduct maintenance on the UPS systems. Maintenance will start from 7AM Central and last till 10PM Central.

We are removing an unused UPS from the power path and adding generator redundancy to the replacement UPS.

Power and cooling redundancy will be degraded for periods of time during the maintenance window.